The information on this page was correct at the time of publishing (December 2022). The project has since evolved and we would encourage you to read our September update for more information.

Site selection principles

To give some background into how the project has reached its current phase, this section includes information about our site selection process, in particular the principles we have followed.

North Falls and our consultants have worked to identify suitable locations for the project's infrastructure as part of our ongoing environmental assessment and to support our further design. We have used an iterative process incorporating input from a range of disciplines including environmental, engineering design, technical, planning as well as from stakeholders. Consultation feedback continues to be a critical element of the site selection process and by this we mean stakeholder and public consultation as well as consultation with other projects.

Offshore site selection

The offshore export cable corridor site selection process commenced in 2020, with formal stakeholder consultation the following year. Selection has been based on the following principles:

  • Selection of the most direct route from array to preferred landfall search area, in balance with the other key principles

  • Avoid, or minimise direct impact to, designated/protected environmental sites where possible

  • Minimise impact on other sea users and navigational safety

  • Avoid significant sandbank features where possible

  • Avoid aggregate dredging areas, anchorages and dumping grounds where possible

  • Avoid locations of known archaeological importance where practicable

  • Avoid existing operational or planned offshore wind farm sites

  • Avoid routing through offshore oil and gas sites

  • Minimise the number of subsea cable/pipeline crossings, and

  • Explore options to reduce cable footprint with other known developers

This diagram shows the step-by-step process used in refining the location of the North Falls infrastructure to date

Site selection process diagram

Landfall site selection

The landfall site selection began consultation in early 2021 with the overarching principles to:

  • Avoid direct significant impacts with European, national and local ecologically designated sites

  • Avoid direct significant impacts with landscape and cultural heritage designations

  • Avoid areas with substantial infrastructure or urban/recreational land use such as housing or caravan parks

  • Maintain a required separation distance from other offshore cables and pipelines

  • Ensure the potential horizontal directional drill length is achievable (up to four drills), and

  • Consider options that could facilitate co-location of underground cable landfall infrastructure with other known developers who may be connecting to the national grid at a similar location and therefore using a similar landfall

Onshore cable corridor selection

North Falls began its onshore cable route selection process in 2021 adhering to the following principles wherever possible:

  • Routing should be kept as straight and as short as practicable - avoiding tight bends

  • Avoid residential titles (including whole gardens) where possible

  • Avoid direct significant impacts with European, national and local ecologically designated sites

  • Avoid direct significant impacts with landscape and cultural heritage designations

  • Avoid direct significant impacts to mature woodland, historic woodland and important hedgerows

  • Minimise the number of:

    • crossings of assets such as utilities, and of road and rail crossings

    • hedgerow and watercourse crossings, and

  • Consider options that could facilitate co-location of cable infrastructure with other known developers who may be connecting to the national grid at a similar location.

Onshore substation site - selection of options

The key principles underpinning the site selection process for North Falls onshore substation are that options should (all factors being equal):

  • Be located as close as possible to the National Grid substation - with a maximum distance of 3km (to reduce electrical losses)

  • Include up to 0.2km2 of land for the substation, temporary works/construction compound as well as landscaping, flood defence and drainage and other necessary infrastructure

  • Include an allowance for temporary and permanent access to the highway network

  • Consider sharing land and minimising spatial extent of effects, subject to the agreement of National Grid

  • Facilitate co-location with other known developers who may be connecting to the national grid at a similar location

  • Consider options with the least environmental effects when considered with other known developers' proposed substation location(s)

  • Be technically feasible and economically viable and be subject to a constructability review

  • Comply with requirements of National Policy Statement provisions and other key national and local policy relevant to alternatives and site selection

  • Avoid land within residential titles (including whole gardens) where possible

  • Avoid direct significant impacts with European, national and local ecologically designated sites

  • Avoid direct significant impacts with landscape and cultural heritage designations

  • Minimise significant impacts to the special qualities of Areas of Outstanding Natural Beauty

  • Avoid mature woodland and historic woodland

  • Avoid areas that fall within Flood Zone 3 and areas of contaminated ground

  • Locations should take advantage of the screening provided by land form and existing features and the potential use of site layout and levels to keep intrusion into surrounding areas to a reasonably practicable minimum,* and

  • Options should keep the visual, noise and other environmental effects to a reasonably practicable minimum.*

* aligned to the Horlock Rules which apply to the location and design of substations.

Horlock Rules for siting and designing substations

Photo of public footpath sign
Photo of public footpath